Malton Go Station

Owner: METROLINX / GO TRANSIT
 Type: Public Transit / Infrastructure
 Cost: $1,000,000.00
 Architect: JOHNSTON ARCHITECT
 Engineer: Y & V ENGINEERING
G.C: B.GOTTARDO CONSTRUCTION
Challenges: Galvanized curved roof canopy frames made from HSS steel section. Fully welded connection for esthetic view about 600 feet long. Fabricated in 16 ft. Wide 45 ft. Long segments in shop. Shop fabrication allowed quality work, proper alignment. Segmented frames reduced erection time at site by 50%. Two levels parking and elevator access structure. Erection work carried out with CN Rail regulation & fully operational rail corridor without shutdown, stoppage to service.

 

 